Three prices for one Lloyd District food hall
An $8.7 million project budget, a $6.35 million contracting request and $351,932 for demolition describe different commitments at 910 NE Martin Luther King Jr. Boulevard.

- November estimate for the whole project
- $8.7m
- Construction authority sought, demolition included
- $6.35m
- Increase over January’s $7.5m estimate
- 16%
Inside Prosper Portland’s November 18 board packet, the renovation planned across from the Oregon Convention Center carries three different price tags. Adding them produces a number the agency never budgeted. The smallest item, an existing demolition and abatement contract, is already inside the larger construction authority staff requested.
The staff report puts that existing contract with Owen Gabbert LLC at $351,932. It says interior work was underway, with completion scheduled for December 4. Staff were still negotiating a maximum price for the main construction contract. Their request would let the executive director award a combined total of up to $6.35 million for specified public improvements, including the demolition already contracted.
The larger $8.7 million estimate includes design, permitting and venue setup. In January the preliminary estimate had been $7.5 million. That is a $1.2 million increase, or 16 percent. Among the changes was a revised $1.06 million estimate to equip and set up the venue. ChefStable, the intended operator, had committed $500,000 toward setup. A higher estimate is a cost to cover, not evidence that the operator doubled its contribution.
Metro is also in the financing. Staff said Metro approved a $3 million loan in August. The January term sheet describes advances against construction invoices and lien waivers. The agency would eventually have to repay principal and interest. Loan proceeds therefore cannot also be counted as extra project cost or as a grant.
The November report identified roughly $200,000 in savings or partner funding still to find to stay within the district’s adopted budget. Staff discussed possible savings, grants and unused contingency. For the ten planned food carts and their future customers, the next meaningful records will be the executed main contract, any gap funding and an operating opening. The public project page currently targets fall 2027.
How we checked this
We matched the November 18 agenda request and budget to the January financing terms and public project profile. The 16% figure is ($8.7m − $7.5m) ÷ $7.5m. This article records the request and existing demolition contract. It does not count the requested ceiling as a payment.